Madhya Bhotekoshi IPO Result date is fixed now. According to issue manager, the IPO result published on Friday, October 29, 2021. The pre-allotment of Madhya Bhotekoshi IPO was completed on Oct 27, 2021. The Madhya Bhotekoshi IPO was opened for general public from Ashwin 20 to Ashwin 25, 2078. A total of the offered 90,00,000 units shares; 4% of the total offered shares (3,60,000 units) have been allocated for the employees of the company and 5% of the total offered shares (4,50,000 units) have been allocated for the mutual funds. The remaining 81,90,000 units are opening for the general public now. You can check IPO Result from MeroShare CDSC when it will be published on Madhya Bhotekoshi IPO Result date.   

How to Check IPO Result of Madhya Bhotekoshi Ltd

Are you looking for How to Check IPO Result of Madhya Bhotekoshi Ltd ? If yes, we shares the five ways, you can check the IPO result of Madhya Bhotekoshi IPO Result on the published date. You can find first and fast of the IPO result if you will try all the methods.

Madhya Bhotekoshi IPO Result Date
Madhya Bhotekoshi IPO Result Date
  1. Check Madhya Bhotekoshi IPO Allotment from  iporesult.cdsc.com.np ipo result 2021 (CDS and Clearing Limited)
  2. Check Madhya Bhotekoshi IPO from Global IME Capital IPO Result Official page
  3. Check Madhya Bhotekoshi IPO Result from NIBL Ace Capital IPO Result or NIBL Ace Capital Mero Share
  4. Check Madhya Bhotekoshi IPO Result from Prabhu Capital IPO Result or Prabhu Capital Mero Share
  5. Check Madhya Bhotekoshi IPO Result from Civil Capital Market IPO Result or Civil Capital Market Mero Share
  6. You can also check IPO Result from Mero share Account www.meroshare.cdsc.com.np
  7. You can also check IPO Result from IPO Result App or Nepali Share App

Global IME Capital Limited of Madhya Bhotekoshi Limited IPO is the issue manager and NIBL Ace Capital Limited is the co-issue manager who secured the IPO. The Madhya Bhotekoshi company Limited has 1,50,00,000 registered shares. Out of which 40,50,000 shares has issued to the public and employees. The company’s paid-up capital is 27%.

CARE Ratings for Madhya Bhotekoshi IPO

Global IME Capital Limited is the issue manager for the IPO. The sub-issue managers are NIBL Ace Capital, Prabhu Capital, Laxmi Capital, Civil Capital, Sanima Capital and CBIL Capital. The company has already issued 10% of the company’s capital to the locals and 15% to the general public issued now. The Madhya Bhotekoshi ipo got the ‘CARE-NP IPO Grade 4+’ to the proposed Initial Public Offering (IPO) of Madhya Bhotekoshi Jalavidyut Company Limited (MBJCL). ‘CARE-NP IPO Grade 4+’ indicates Below Average Fundamentals in performance. 

Madhya Bhotekoshi Capacity

Madhya Bhotekoshi Capacity is 102 MW. Madhya Bhotekoshi Jalavidyut Company Ltd. is a public limited company established on July 29, 2010. It is promoted by NEA (a GoN Corporation) and Chilime Hydropower Company Limited (CHCL, 51% subsidiary of NEA) for setting up 102 MW run-of-river, Middle Bhotekoshi Hydroelectric Project in Sindhupalchowk district of Nepal.

Madhya bhotekoshi ipo price

Madhya bhotekoshi ipo price is Rs. 100 for apply of IPO. This will be traded in secondary market at Rs.405.33. The estimated price of Madhya bhotekoshi ipo will reach up to Rs. 700 to Rs. 900.  So, this is the good news for Madhya bhotekoshi ipo investors.

Madhya Bhotekoshi IPO for Public – Madhya Bhotekoshi IPO 2021

Madhya Bhotekoshi IPO for Public opened in 2021 and it gives us the investment opportunities who wants to invest small amount for long term or short term earning. Before applying, learn about company from here below;

Madhya Bhotekoshi IPO Project: Introduction

Type of Project:Run-of-River (ROR)
Design flow:50.8 m3/sec
Gross Head:235 m
Headworks:Gated Weir Type with Undersluice and Side Intake
Desanding Basin Type & Size:Surface, 100 m(l) x 13 m(w) x 8.5 m(h)
Tunnel Length & Size:7124 m x 5.7 m(w) x 5.7 m(h)
Powerhouse Type & Size:Surface Powerhouse 52 m(l) x 15 m(b) x 25.5 m(h)
Turbine:
Unit Capacity:
Type, Orientation & Number
Francis, Vertical Axis & 3 Nos. 34 MW
Generator Unit Capacity & Nos.:40 MVA & 3 Nos.
Installed Capacity:102 MW (3 x 34 MW)
Annual Salable Energy:542.2 GWh
Dry Energy:83.7 GWh
Wet Energy:458.5GWh
Transmission Line Length/ Voltage:4 km/Single Circuit 220 kV

Status of Madhya Bhotekoshi Project

  • Certificate of Company Registration & Certificate of Commencement of Business were received from Office of Company Registrar (OCR) on July 29, 2010 & August 29, 2011 respectively.
  • Survey License for Power Generation received from Ministry of Energy on April 8, 2011.
  • Connection Agreement for power evacuation was done with NEA on August 25, 2011 and Power Purchase Agreement (PPA) was signed on November 14, 2011.
  • Tripartite Loan Agreement between was signed between EPF, CHCL and the company on December 8, 2011
  • The project started construction by February 11, 2014 and targeted to complete the project by the end of December 2020.
  • Consulting services is awarded to Tractebel Engineering GmbH( formerly Lahmeyer Internation GmbH(LI)) in association with TMS.
  • Detailed Project Report has been completed.
  • Hydrological measurements at headworks and powerhouse site is being continued.Surface geological investigation including drilling in headworks and powerhouse as well as sub-surface exploration with HRT has been carried out to determine the geological condition in the key structure locations.
  • Land acquisition process is in Final Stage of completion.
  • Test Adit is completed by Himal Hydro Construction Ltd.
  • Camp Facilities are constructed.
  • Diversion Tunnel Constructed by Himal Hydro Construction Ltd.
  • EIA approved 12 th November 2013
  • Generation License received December 03, 2013
  • Lot-1 (Civil and Hydromechanical works) contract is awarded to Guangxi Hydroelectric Construction Bureau.
  • Lot2 Electro-Mechanical Contract is Awarded to Andritz Hydro Private Limited in association with Trade Link International.
  • Transmission Line works Contract is Awarded to Urja-AC JV Lalitpur, Nepal on July 27, 2018.
  • IEE of Transmission Line approved on May 23, 2019 (2076/02/09)

We welcome your comment without any link.